Sealing Water Ingress in a Major Industrial Pipeline at Tata Steel, Port Talbot

Sub-industry

Industrial

Problems

Pipe Water Ingress

Location

Port Talbot, Wales

Year

2026

Solutions

Resin Injection

Technology

Teretek®

Mainmark helped Tata Steel eliminate water ingress affecting a critical industrial pipeline at Port Talbot using its proprietary Teretek® resin injection technology. The solution sealed active ingress pathways, prevented further water penetration and protected the asset from ongoing deterioration without the need for major excavation or replacement works.

Completed in just five days, the project restored confidence in the long-term performance of the pipeline while allowing site operations to continue uninterrupted.

The Challenge

Water ingress was occurring through a large-diameter industrial pipeline, creating operational concerns and the potential for ongoing deterioration of surrounding infrastructure. The source of the ingress needed to be identified and sealed quickly to prevent further water penetration and avoid disruption to site operations.

The client required a rapid, non-disruptive solution capable of sealing ingress pathways and protecting the asset without extensive excavation.

The Solution

Mainmark carried out a detailed site assessment to identify likely ingress points and determine the most effective treatment approach.

Using 2,150kg of Teretek® material, the team injected expanding geopolymer resin into the affected area, where it:

  • Filled voids and water migration paths

  • Created a dense, impermeable barrier

  • Sealed active water ingress pathways

  • Protected the pipeline from further water-related deterioration

The treatment achieved effective remediation without major excavation, asset replacement or interruption to ongoing site activities.

The Results

Mainmark successfully eliminated water ingress and protected the pipeline from further deterioration.

Project Outcomes

  • Installed 2,150kg of Teretek® material

  • Successfully stopped water ingress into the pipeline

  • Completed works without major excavation

  • Avoided disruption to site operations

  • Protected critical infrastructure from ongoing deterioration

  • Extended the service life of the existing asset

Verification following treatment confirmed that water ingress had been successfully arrested, with no further evidence of active water penetration.

Key Benefits

Water Ingress Eliminated

Created an impermeable barrier that prevented further water penetration into the pipeline system.

Minimal Disruption

Delivered a rapid solution without major excavation or interruption to operational activities.

Extended Asset Life

Protected critical pipeline infrastructure and avoided the need for premature replacement.

Lower Environmental Impact

Retained the existing asset and avoided the material consumption, waste generation and environmental impacts associated with more invasive repair methods.

Expert Insight

"The water ingress affecting this critical pipeline required a solution that could be delivered quickly, safely and with minimal disruption to ongoing operations. Mainmark's Teretek® injection methodology successfully sealed the ingress pathways, filled associated voids and restored confidence in the long-term performance of the asset without the need for extensive excavation or replacement works."

David Hedley, Infrastructure Lead

Looking to Stop Water Ingress Without Excavation?

Mainmark's Teretek® resin injection technology provides a fast, non-intrusive solution for sealing water ingress, filling voids and protecting critical infrastructure assets without disruptive excavation or replacement works.

Our Memberships and Accreditations

A diverse group of passionate professionals, each bringing unique skills and experiences to drive innovation and excellence in every project we undertake.

Mainmark’s specialised in-house solutions

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.

Get in Touch

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.

Sealing Water Ingress in a Major Industrial Pipeline at Tata Steel, Port Talbot

Sub-industry

Industrial

Problems

Pipe Water Ingress

Location

Port Talbot, Wales

Year

2026

Solutions

Resin Injection

Technology

Teretek®

Mainmark helped Tata Steel eliminate water ingress affecting a critical industrial pipeline at Port Talbot using its proprietary Teretek® resin injection technology. The solution sealed active ingress pathways, prevented further water penetration and protected the asset from ongoing deterioration without the need for major excavation or replacement works.

Completed in just five days, the project restored confidence in the long-term performance of the pipeline while allowing site operations to continue uninterrupted.

The Challenge

Water ingress was occurring through a large-diameter industrial pipeline, creating operational concerns and the potential for ongoing deterioration of surrounding infrastructure. The source of the ingress needed to be identified and sealed quickly to prevent further water penetration and avoid disruption to site operations.

The client required a rapid, non-disruptive solution capable of sealing ingress pathways and protecting the asset without extensive excavation.

The Solution

Mainmark carried out a detailed site assessment to identify likely ingress points and determine the most effective treatment approach.

Using 2,150kg of Teretek® material, the team injected expanding geopolymer resin into the affected area, where it:

  • Filled voids and water migration paths

  • Created a dense, impermeable barrier

  • Sealed active water ingress pathways

  • Protected the pipeline from further water-related deterioration

The treatment achieved effective remediation without major excavation, asset replacement or interruption to ongoing site activities.

The Results

Mainmark successfully eliminated water ingress and protected the pipeline from further deterioration.

Project Outcomes

  • Installed 2,150kg of Teretek® material

  • Successfully stopped water ingress into the pipeline

  • Completed works without major excavation

  • Avoided disruption to site operations

  • Protected critical infrastructure from ongoing deterioration

  • Extended the service life of the existing asset

Verification following treatment confirmed that water ingress had been successfully arrested, with no further evidence of active water penetration.

Key Benefits

Water Ingress Eliminated

Created an impermeable barrier that prevented further water penetration into the pipeline system.

Minimal Disruption

Delivered a rapid solution without major excavation or interruption to operational activities.

Extended Asset Life

Protected critical pipeline infrastructure and avoided the need for premature replacement.

Lower Environmental Impact

Retained the existing asset and avoided the material consumption, waste generation and environmental impacts associated with more invasive repair methods.

Expert Insight

"The water ingress affecting this critical pipeline required a solution that could be delivered quickly, safely and with minimal disruption to ongoing operations. Mainmark's Teretek® injection methodology successfully sealed the ingress pathways, filled associated voids and restored confidence in the long-term performance of the asset without the need for extensive excavation or replacement works."

David Hedley, Infrastructure Lead

Looking to Stop Water Ingress Without Excavation?

Mainmark's Teretek® resin injection technology provides a fast, non-intrusive solution for sealing water ingress, filling voids and protecting critical infrastructure assets without disruptive excavation or replacement works.

Our Memberships and Accreditations

A diverse group of passionate professionals, each bringing unique skills and experiences to drive innovation and excellence in every project we undertake.

Mainmark’s specialised in-house solutions

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.

Get in Touch

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.

Sealing Water Ingress in a Major Industrial Pipeline at Tata Steel, Port Talbot

Sub-industry

Industrial

Problems

Pipe Water Ingress

Location

Port Talbot, Wales

Year

2026

Solutions

Resin Injection

Technology

Teretek®

Mainmark helped Tata Steel eliminate water ingress affecting a critical industrial pipeline at Port Talbot using its proprietary Teretek® resin injection technology. The solution sealed active ingress pathways, prevented further water penetration and protected the asset from ongoing deterioration without the need for major excavation or replacement works.

Completed in just five days, the project restored confidence in the long-term performance of the pipeline while allowing site operations to continue uninterrupted.

The Challenge

Water ingress was occurring through a large-diameter industrial pipeline, creating operational concerns and the potential for ongoing deterioration of surrounding infrastructure. The source of the ingress needed to be identified and sealed quickly to prevent further water penetration and avoid disruption to site operations.

The client required a rapid, non-disruptive solution capable of sealing ingress pathways and protecting the asset without extensive excavation.

The Solution

Mainmark carried out a detailed site assessment to identify likely ingress points and determine the most effective treatment approach.

Using 2,150kg of Teretek® material, the team injected expanding geopolymer resin into the affected area, where it:

  • Filled voids and water migration paths

  • Created a dense, impermeable barrier

  • Sealed active water ingress pathways

  • Protected the pipeline from further water-related deterioration

The treatment achieved effective remediation without major excavation, asset replacement or interruption to ongoing site activities.

The Results

Mainmark successfully eliminated water ingress and protected the pipeline from further deterioration.

Project Outcomes

  • Installed 2,150kg of Teretek® material

  • Successfully stopped water ingress into the pipeline

  • Completed works without major excavation

  • Avoided disruption to site operations

  • Protected critical infrastructure from ongoing deterioration

  • Extended the service life of the existing asset

Verification following treatment confirmed that water ingress had been successfully arrested, with no further evidence of active water penetration.

Key Benefits

Water Ingress Eliminated

Created an impermeable barrier that prevented further water penetration into the pipeline system.

Minimal Disruption

Delivered a rapid solution without major excavation or interruption to operational activities.

Extended Asset Life

Protected critical pipeline infrastructure and avoided the need for premature replacement.

Lower Environmental Impact

Retained the existing asset and avoided the material consumption, waste generation and environmental impacts associated with more invasive repair methods.

Expert Insight

"The water ingress affecting this critical pipeline required a solution that could be delivered quickly, safely and with minimal disruption to ongoing operations. Mainmark's Teretek® injection methodology successfully sealed the ingress pathways, filled associated voids and restored confidence in the long-term performance of the asset without the need for extensive excavation or replacement works."

David Hedley, Infrastructure Lead

Looking to Stop Water Ingress Without Excavation?

Mainmark's Teretek® resin injection technology provides a fast, non-intrusive solution for sealing water ingress, filling voids and protecting critical infrastructure assets without disruptive excavation or replacement works.

Our Memberships and Accreditations

A diverse group of passionate professionals, each bringing unique skills and experiences to drive innovation and excellence in every project we undertake.

Mainmark’s specialised in-house solutions

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.

Get in Touch

Our dedicated team of experts is committed to understanding your unique needs and objectives, working closely with you to develop and execute.